Bay Area Images

Waterfront Plaza
Oakland
Alameda County

Air Quality Fact

Weather patterns play a fundamental role in determining whether air pollution will disperse or accumulate.

Give Us Your Feedback



select


(500 character limit)
 

I would like a response.
(Allow 5-7 business days)
 

 

Utility Buttons

  • Email This Page
  • Print
  •  Save & Share Share

BAAQMD Webcasts

Recent Webcasts

5/16/2012
Board of Directors Special Meeting

More Information:
5/16/2012 Agenda
(442 kb PDF, 8 pgs)

5/2/2012 Board of Directors Meeting
More Information:
5/2/2012 Agenda
(1 Mb PDF, 52 pgs)

4/18/2012 Board of Directors Meeting
More Information:
4/18/2012 Agenda
(4 Mb PDF, 315 pgs)

Board Archives

Agendas, Minutes and Media

HelpWebcast Support
System & player requirements, RSS feeds & mobile alternatives.

BAAQMD on iTunes

iTunes Audio Podcasts
iTunes Video Podcasts

Contacts

Individuals

  • Gregory Stone
  • Supervising Air Quality Engineer, Engineering
  • 415 749-4745

Accelerated Permit Program

The Accelerated Permit Program allows a qualifying air pollution source or abatement device to be installed and operated under a temporary Permit to Operate, while the applicant waits for the formal permit to be issued. Under this program certain types of equipment can startup on the same day the permit application is filed. The District issues the formal permit to Operate after the evaluation process is complete.

Program Criteria

In order to take advantage of this program, the following criteria must be met:

Uncontrolled source emissions are less than 10 lbs per highest day or equipment is pre-certified,

Emissions of toxic compounds do not exceed trigger levels (most diesel engines will exceed the trigger levels) and,

Equipment is located more than 1,000 feet from a school.

 

Application Process

Applicants must submit a permit application consisting of:

  • Completed permit application form and source data form(s)
  • Certification that all Accelerated Permitting Program criteria are met
  • Payment of applicable fees

Air District authorizes applicant to immediately install and operate equipment.

Permit to Operate is issued within 35 working days of receipt of completed application.